Opponents of the Keystone XL pipeline demonstrate on the Dodge Street pedestrian bridge during rush hour in Omaha, Neb., on Nov. 1, 2017. A federal judge in Montana has blocked construction of the $8-billion Keystone XL pipeline to allow more time to study the project’s potential environmental impact. THE CANADIAN PRESS/AP, Nati Harnik

U.S. judge blocks construction of $10-billion Keystone XL pipeline

Two other export pipelines - expansion of the TransMountain pipeline and Enbridge Inc.’s Line 3 pipeline replacement - also face uncertainty

TransCanada’s $10-billion Keystone XL pipeline project has suffered another setback after a U.S. federal judge blocked its construction to allow more time to study the potential environmental impact.

The Great Falls Tribune reports U.S. District Judge Brian Morris’ order on Thursday came as the Calgary-based energy giant was preparing to build the first stages of the oil pipeline in northern Montana.

Indigenous and environmental groups had sued TransCanada and the U.S. Department of State after Nebraska authorities approved an alternative route to the one TransCanada had proposed through the state.

The groups argued the U.S. State Department violated several acts in issuing a presidential permit for the pipeline without a proper environmental assessment of the changed route.

Morris said in his decision Thursday the government’s analysis didn’t fully study the cumulative effects of greenhouse gas emissions, the effects of current oil prices on the pipeline’s viability or include updated modelling of potential oil spills.

The proposed 1,897-kilometre pipeline would carry crude from Hardisty, Alta., to Steel City, Neb.

READ MORE: Nebraska approves TransCanada’s Keystone XL pipeline

Two other export pipelines, the expansion of the TransMountain pipeline sold to the federal government and Enbridge Inc.’s Line 3 pipeline replacement, also face uncertainty.

The Associated Press

Like us on Facebook and follow us on Twitter.

Just Posted

Happy Easter everyone!

Youngsters are excited for the holiday

UCP candidate Nate Horner triumphs in Drumheller-Stettler riding

Horner looking forward to moving ahead with UCP policies in the coming months

Kenney talks pipelines with Trudeau after election win, calls it cordial

Almost a year ago Kenney dismissed Trudeau as a dilettante and a lightweight

Trade show fun!

Annual Stettler Trade Show proves a hit with local residents

Stettler residents cast their votes

Polling station closes at 8 p.m.

‘Open for business:’ Jason Kenney’s UCP wins majority in Alberta election

The UCP was leading or elected in 63 of 87 seats Tuesday night

Kirkland Signature veggie burgers recalled due to possible metal fragments

Recalled products came in 1.7 kg packages with a best before date of Apr. 23, 2019

Parents of 13 who tortured children get life after hearing victims

One of their daughters fled their home and pleaded for help to a 911 operator

Flooding, climate change force Quebecers to rethink relationship with water

Compensation for victims of recurring floods limit to 50% of a home’s value, or a maximum of $100,000

Storms blast South, where tornadoes threaten several states

9.7 million people in the Carolinas and Virginia at a moderate risk of severe weather

Private cargo ship brings Easter feast to the space station

There are three Americans two Russians and one Canadian living on the space station

Notre Dame rector: “Computer glitch” possible fire culprit

The fire burned through the lattice of oak beams supporting the monument’s vaulted stone ceiling

Undercover cops don’t need warrant to email, text suspected child lurers: court

High court decision came Thursday in the case of Sean Patrick Mills of Newfoundland

VIDEO: Trump tried to seize control of Mueller probe, report says

Special counsel Robert Mueller’s report revealed to a waiting nation Thursday

Most Read