Third phase to make Capital Power’s Whitla Wind project Alberta’s largest

Third phase to make Capital Power’s Whitla Wind project Alberta’s largest

CALGARY — Capital Power Corp. says a $92-million expansion of its Whitla Wind power facility in southern Alberta will make it the largest in the province.

The Edmonton-based company says it will add 54 megawatts of capacity by late 2021 through the third phase of the project, taking it to 353 MW.

Subject to regulatory approvals, the third phase is to be constructed concurrently with the 97-MW second phase announced in December, shortly after the 202-MW initial phase was placed in service.

Alberta ranks third in Canada with an installed wind energy capacity of almost 1,700 MW, according to the Canadian Wind Energy Association.

Whitla Wind 3 is to consist of 15 wind turbines and use the same technology in operation at Whitla Wind 1.

The projects are expected to generate carbon credits to offset Capital Power’s carbon compliance costs from its Alberta thermal power generation facilities.

“Once all three phases of the Whitla Wind facility are completed by the end of 2021, it will be Alberta’s largest wind facility with 353 megawatts of generation capacity,” said Capital CEO Brian Vaasjo.

This report by The Canadian Press was first published June 22, 2020.

Companies in this story: (TSX:CPX)

The Canadian Press

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Comments are closed

Just Posted

Calgary singer Erin Ross to be featured at ‘Entertainment in the Park’ July 15th

Roots/blues musician can hardly recall a time when she wasn’t passionate about performing

PHOTOS: Despite some soggy weather, fireworks capped off Canada Day in Stettler

The skies above West Stettler Park were lit up to help celebrate the nation’s birthday

Red Deer remains at two active COVID-19 cases

Alberta confirms 94 new cases over past two days

Stettler Board of Trade continues to help businesses navigate challenging times

‘Christmas in July’ is another current means of encouraging folks to ‘shop local’

A look back – marking the opening of the new Town Office on the corner of Main Street and 49th Ave. in 1966

The opening was attended by deputy premiere A. J. Hooke, who acted as the main speaker at the ceremony

PODCAST: Black Lives Matter in central Alberta Part 2

More insight into the Black Lives Matter movement of central Alberta

PODCAST: Black Lives Matter in central Alberta Part 2

More insight into the Black Lives Matter movement of central Alberta

Le Chateau starts work on producing 500,000 hospital gowns in Canada

Another Canadian company pivots to produce PPE

Canadian engineer released from Egypt needs treatment, family says

Canadian engineer released from Egypt needs treatment, family says

Inquiry into mass shooting in Nova Scotia facing delays due to ‘technicalities’

Inquiry into mass shooting in Nova Scotia facing delays due to ‘technicalities’

Quebec tractor driver charged after accident kills three children, injures seven

Quebec tractor driver charged after accident kills three children, injures seven

Most Read